2017 Journey Forward Pastoral Campaign

The Mercy Center has been completed!

CLICK LINKS BELOW TO SEE THE WEEKLY CONSTRUCTION PHOTOS

Week 1
Week 2
Week 3
Weeks 4 & 5
Week 6
Weeks 7 & 8
Week 9
Week 10
Week 11
Week 12
Week 13
Week 14
Week 15
Week 16
Week 17
Week 18
Week 19
Week 20

Week 21
Week 22
Week 23
Week 24
Week 25
Week 26
Week 27
Week 28
Week 29
Week 30 – Gazebo Grand Opening!
Week 31

Week 32
Week 33
Week 34
Week 35
Week 36
Week 37
Week 38
Week 39
Week 40
Week 41
Week 42
Week 43
Week 44
Week 45
Week 46
Week 47
Week 48
Week 49
Week 50
Week 51
Week 52
Week 53
Week 54
Week 55
Week 56
Week 57
Week 58
Week 59
Week 60
Week 61
Week 62
Week 63

  1. GroundbreakingCLICK HERE FOR MORE PICTURES FROM THE GROUNDBREAKING CEREMONY

February 20, 2015 – Plans submitted for permits

May 6, 2015 – Construction trailer moved onto Campus

May 11, 2015 – Construction fencing installed

June 2, 2015 – Groundbreaking Ceremony

July 22, 2015 – Construction on Gazebo began

August 17, 2015 – Received the Gazebo Final PermitCLICK HERE TO READ COMMENTS FROM OUR CAPITAL CAMPAIGN COMMITTEE

To learn more about the Journey Forward Pastoral Campaign and how you can get involved contact the Campaign Office at (561) 952-2838 or E-mail the Development Director: horton_wendy@stjoan.org

 

newmercycenter_comments